pert-estimate
v1.0.0
Published
Calculates estimate(s) based on the PERT method by using "most likely time", "optimistic time", and "pessimistic time"
Downloads
4
Readme
pert-estimate
Calculate estimate(s) based on the PERT method by using "most likely time", "optimistic time", and "pessimistic time".
Installation
$ npm install --save pert-estimate
Usage
var pert = require('pert-estimate');
/**
* Expected duration
*
* Two different ways of specifying arguments;
* individual arguments or as an object.
*
* Order: optimistic, nominal, pessimistic
*/
console.log(pert.expectedDuration(1, 3, 14)); // 4.5
console.log(pert.expectedDuration({
optimistic: 1,
nominal: 3,
pessimistic: 14
}));
/**
* Standard deviation
*/
console.log(pert.standardDeviation(1, 3, 14)); // 2.16
console.log(pert.standardDeviation({
optimistic: 1,
nominal: 3,
pessimistic: 14
}));
License
MIT-licensed. See LICENSE.